The National Highways Authority of India (NHAI) has restructured the 195.13-km Amaravati Outer Ring Road into two construction packages, with an estimated cost of ₹15,116.45 crore. According to reports from The Times of India, the revised tender structure is aimed at taking forward the development of the access-controlled greenfield corridor around the Amaravati capital region. The project will include a four-lane spur connecting Guntur with Narakodur, alongside the main six-lane ring road, with the highway planned as a six-lane, access-controlled greenfield road. The highway is intended to improve connectivity around the capital region and provide an alternative route for traffic moving through the wider Vijayawada-Guntur-Amaravati area.
Under the revised arrangement, the first package will cover an 87.63-km stretch between Kanchikacherla and Vuyyuru, with an estimated construction cost of ₹7,873.40 crore. The second package will span 107.50 km, covering the stretch from Vuyyuru to Kanchikacherla and incorporating the four-lane spur road between Guntur and Narakodur, with an estimated cost of ₹7,243.05 crore. Together, the two packages will account for the entire 195.13-km Amaravati ORR project, with the combined estimated expenditure pegged at ₹15,116.45 crore. The project structure represents a significant shift from NHAI's initial approach of tendering the project under four separate packages to the current two-package arrangement following suggestions from the Public Private Partnership Appraisal Committee (PPPAC).
NHAI had initially invited bids for the project under four separate packages, but subsequently restructured the arrangement into two packages following suggestions from the Public Private Partnership Appraisal Committee (PPPAC). As reported by The Times of India, the financing and implementation model has been revised from the Hybrid Annuity Mode (HAM) to the Build-Operate-Transfer (BOT) Toll-Cum-Annuity model under the public-private partnership framework. Under the revised tender schedule, January 15, 2027, is the deadline for submitting bids, while the technical and financial proposals are scheduled to be opened on January 18 at 11.30 am.
Land acquisition is a major component of the infrastructure project, with the government planning to acquire approximately 7,400 acres spread across 97 villages in five districts for the construction of the ORR. According to The Times of India, an estimated ₹5,315 crore has been earmarked for land acquisition, in addition to the projected construction expenditure of ₹15,116.45 crore. The scale of land acquisition highlights the extent of the proposed road network, which is expected to connect several parts of the Amaravati capital region and improve access to surrounding urban and rural areas. This substantial land requirement underscores the comprehensive nature of the infrastructure development project.