Two homebuyers filed a case against a builder over an apartment project where they had signed the sale agreement in 2014 with possession due by June 30, 2017. According to reports from The Times of India, the flat's consideration was ₹1.95 crore, but by the time of the complaint, the buyers had paid ₹2.06 crore, including the consideration paid to the promoter, stamp duty, registration charges and applicable taxes. The buyers approached MahaRERA seeking possession along with interest for the delay, leading to the current legal proceedings.
In March 2021, the Maharashtra Real Estate Appellate Tribunal directed the promoter to pay interest at the State Bank of India's highest marginal cost of lending rate plus 2% on the amount paid, from July 1, 2017, until possession was handed over. As reported by The Times of India, the tribunal also awarded ₹25,000 in costs. The builder challenged this order before the Bombay High Court, arguing that by continuing to pay installments under revised schedules and not objecting to letters announcing new dates, the buyers had accepted the delay. However, the High Court rejected this argument, holding that buyers have an unconditional right to monthly interest under Section 18 of RERA.
According to Gaurav Dasgupta, Partner at Khaitan & Co, as reported by The Times of India, this is one of the most homebuyer-friendly rulings seen this year. The court examined whether accepting delayed performance could deprive homebuyers of their right to interest under Section 18 of RERA and held that the statutory protection could not be made conditional on giving the notice contemplated under Section 55 of the Contract Act. The court rejected the developer's argument, stating that RERA is a special act for real estate which overrides a general act like the Contract Act when there is a conflict between the provisions.
The developer argued that the buyers' conduct showed acceptance of revised possession dates and invoked contractual force majeure provisions and the COVID-19 pandemic. However, as reported by The Times of India, the court noted that the appellate tribunal found 'no authentic evidence' that the buyers had accepted the revised possession date or waived their right to interest. The court also examined the developer's communications, observing that these primarily informed buyers about the delay and offered assurances about completion, with the revised timelines being 'couched in a manner so as to be in nature of information requiring no further acts by the allottees'.
The Bombay High Court dismissed the builder's appeal on June 18, 2026, upholding the direction to pay interest from July 1, 2017, until possession was handed over. According to The Times of India, the ruling has been challenged before the Supreme Court through a special leave petition filed on July 24, 2026. The developer's advocate initially indicated that an out-of-court settlement was being explored, but later stated they want a full-fledged hearing in the appeal. The question the Supreme Court may now address is whether this long-established Contract Act rule has any role left in RERA disputes.