The Road Transport and Highways Ministry has introduced comprehensive new penalties for contractors involved in accident-prone highway projects, marking a significant shift in construction accountability. According to Business Standard, the ministry has capped subcontracting at 30% of project value from the earlier limit of 49%, addressing long-standing concerns about accountability diffusion. Under the new framework, contractors will be given 15 days to rectify errors after the first accident, with the government retaining the right to undertake maintenance and remedial work at the contractor's cost if compliance is not achieved. The penalties escalate dramatically for repeat incidents, with ₹25 lakh per fatality and ₹10 lakh per grievous injury for accidents within 500 metres of the first accident location within one year, and ₹50 lakh per fatality and ₹25 lakh per grievous injury for third accidents occurring within another year.
The Highways Ministry has invoked the newly introduced catastrophic failure clause against two highway developers for major structural failures on National Highways projects. According to reports from Press Trust of India, the provisions allow highway-owning agencies to bar highway developers for two years from bidding for new projects. Such highway builders also face negative ratings that will adversely impact their chances of getting future projects. The Road Transport and Highways Ministry has officially notified these catastrophic events through formal ministry orders, marking a significant enforcement action in highway project oversight. This represents the first time such a clause has been inserted for any EPC work, as confirmed by ministry officials.
The first case involves the four-lane Poondiankuppam-Sattanatharupam section of NH-45 (New NH-32) from km 67 to km 123 in Tamil Nadu under HAM mode. As reported by Press Trust of India, the bid project cost was ₹2,120 crore and was awarded to M/S Poonadinkuppam Sattanathapuram Section Private Limited under a concession agreement. The project had an appointed date of January 20, 2022, with a scheduled completion date of January 19, 2024, and M/s Theme Engineering Services Private Limited was appointed as the independent engineer. According to the ministry's official order, at approximately 0030 hours on April 6, 2026, substantial settlement of the pavement quality concrete of approximately 2 metres was observed on the main carriageway at the approach to the light vehicle underpass at km 105+220 on the Kollidam Bypass. The incident was accompanied by bulging, cracking and horizontal displacement of the reinforced earth.
The second case involves the widening and strengthening of approximately 45 km of NH-727B from km 61.500 near Nawalpur to km 106.495 near Sikanderpur, awarded under EPC mode. According to Press Trust of India, the project was sanctioned for ₹2,061 crore, and EPC work was awarded to the joint venture of VRC Constructions (India) Pvt Ltd and R & C Infra Engineers Pvt Ltd at a contract price of ₹613 crore. The project features a two-lane with paved shoulder/ four-lane with paved shoulder configuration under the engineering procurement and construction mode. Technocrats Advisory Services Pvt Ltd was appointed as the authority engineer for this project. As reported by the ministry's order, an incident occurred on March 25, 2026, at about 1015 hours during the execution of reinforcement works for the viaduct portion of the major bridge over River Ghaghra at Chainage km 77+220. During the lifting and erection of the reinforcement cage for the viaduct pier, a portion of the cage collapsed and fell on workers present at the site, resulting in two fatalities and grievous injury to one person.
The new norms establish a tier-system for performance securities where the percentage is now tied to the contractor's rating, with 3% of contract price for those rated 80% or higher, 4% for those between 70-80%, and 5% for those below 70%. For the lowest tier of contractors, 50% of retention money will be locked till the end of the defect liability period. The ministry has also introduced automatic de-scoping of work if the requisite right of way is not allocated within 270 days of the appointed date. These measures follow the Parliament's Public Accounts Committee (PAC) call in August last year over subcontracting in NH projects, which noted that much of the road infrastructure is executed by subcontractors who might not be accountable under the primary contract framework. The railways ministry similarly reduced permissible subcontracting limits from 70% to 40% in March this year.