Rail Vikas Nigam Limited (RVNL) shares have experienced a dramatic decline, falling 71% from their all-time high of ₹647 reached on July 15, 2024. According to exchange data, the stock has continued its downward trajectory in 2026, declining 48% year-to-date and shedding over 50% from its 52-week high of ₹400.70 recorded on December 29, 2025. During Wednesday's trading session, RVNL shares fell more than 3% to make a low of ₹188.88 on the National Stock Exchange. The stock has dropped roughly 43% over the past six months and about 22% in the last week alone, reflecting heightened investor uncertainty.
RVNL delivered robust second quarter results for FY2027, with consolidated revenue from operations rising to ₹4,700 crore and consolidated net profit climbing to ₹253.7 crore, up 59.04% sequentially and 10.06% year-on-year. The company achieved consolidated PAT of ₹413 crore for H1 FY2027, up 13.25% year-on-year, while EBITDA margin improved to 6.26% from 4.4% in the prior quarter. Operating cash flow turned positive at ₹589 crore in H1 FY2027, after a negative ₹1,250 crore a year earlier. The company's order book stood at ₹90,000 crore as of September 30, 2026, representing a 3.6% quarter-on-quarter decline from ₹93,000 crore in the previous quarter, though management expects ₹25,000 crore in annual order inflow with ₹7,132 crore already received in H1.
RVNL has made significant progress on key projects, with the NMDC contract worth ₹3,500 crore showing ₹369 crore received during H1 FY2027. The BharatNet project, valued at ₹13,000 crore, is progressing well with work across various locations under the DBOM model. The Vande Bharat sleeper train set, a ₹14,400 crore project, is in production at the Latur factory with the first prototype now expected in Q1 FY2028, later than the earlier timeline. The Rishikesh-Karnaprayag rail project, costing ₹37,000 crore, has achieved 79% overall progress with 97% tunnel excavation completed, targeting completion by December 2029. Management highlighted that RVNL contributed 33.53% to total revenue from operations during H1 FY2027, showing an 11% increase from the previous year.
The management has significantly cut its FY27 guidance, reducing revenue growth expectations to around 10% (FY27 revenue of ₹220–230 billion) and PAT growth to 8–10%, down from the earlier projections of ~15% and 15–20% respectively. According to PL Capital, even with the revised guidance, the company needs around 19% year-on-year growth in H2 to achieve targets. The brokerage has adjusted its forecasts, cutting FY28E/FY29E revenue by 13%/6% due to slower execution and inflows, but raised Ebitda by 1%/12% and EPS by 4%/12% as it builds in higher margins. Management expects 10%-15% growth in revenue for the second half as monsoon effects fade, with Q3 and Q4 being the periods when RVNL typically books most of its work.
PL Capital maintains its 'Sell' rating on RVNL while trimming its target price to ₹153 from ₹165, implying a downside of nearly 22% from the previous close of ₹195.50. The brokerage highlighted that RVNL trades at a rich valuation of around 38x FY28E EPS, which it considers expensive given the current operational challenges and execution delays. The revised target price reflects the brokerage's concerns about the company's ability to deliver consistent growth in the near term. Despite the strong quarterly performance and positive cash flow generation, the company continues to face execution timing challenges due to monsoon disruptions and project delays, with the Vande Bharat prototype timeline having slipped which could weigh on sentiment around new business lines.